Minimizing Time and Cost in The Iraqi AEC industry by Adopting Building Information Modeling (BIM) Technique.

Authors

  • Mahmood Maad Mahdi MSc Candidate in Civil Engineering Department, College of Engineering, Salahaddin University-Erbil, Kurdistan Region, Iraq
  • Khalil Ismail Wali Department of Civil Engineering,College of Engineering , Salahaddin University-Erbil, Kurdistan Region, Iraq
  • Burog Abdullhalim Yuosif MSc. In public management, a consultant at the Ministry of Planning, Baghdad, Iraq

DOI:

https://doi.org/10.21271/ZJPAS.32.6.19

Keywords:

Building Information Modeling, Construction Management, Cost overrun, Sustainability, Time overrun.

Abstract

The Architectural, Engineering, and Construction (AEC) industry is essential for its direct influence on the development of any
country, particularly in terms of economy. Thus, problems related to cost and time arise as a global phenomenon in this industry,
particularly in the third world countries like Iraq. The Building information modeling (BIM) technique is considered as the most
adequate technique that overcomes the problems facing the AEC industry. This paper aimed to assess the causes of cost issues and
time delays in the Iraqi AEC industry and to outline the BIM concept and the benefits of its application for solving these
problems. This paper consists of two parts; the first one is the quantitative approach, which was adopted for data collection
through a specially designed questionnaire form; these questionnaires were spread among 50 of the top and middle management in
different construction companies, and other experts in the arena of AEC industry. The results of the statistical analysis showed
that the highest influential factors on cost and time overrun are: inadequate planning and scheduling, selecting inefficient
contractors, change orders, and the errors and mistakes in preparing the bill of quantities and materials (BOQ/BOM) with relative
importance index (RII) of 0.98, 0.87, 0.83 and 0.82 respectively. The second part of this paper reviewed the benefits of applying
BIM and highly recommend this technology to improve the local AEC industry. The application of the BIM technique will lead to
more sustainable design, construction, and project delivery in the Iraqi projects. This paper presents a significant set of
recommendations that demonstrate how BIM technique can be applied to overcome the challenges of the AEC industry in Iraq. It
unlocks the door for further authentic researches on the adoption of BIM technique as an influential and exceptional tool to point
out the issues related to time and cost in the AEC industry in Iraq.

References

ABDUL RAHMAN, I., MEMON, A. H., KARIM, A. &

TARMIZI, A. 2013. Significant factors causing

cost overruns in large construction projects in

Malaysia. Journal of Applied Science, 13, 286-293.

ABDULLAH, M., AZIS, A. A. & RAHMAN, I. A. 2009.

Potential effects on large mara construction

projects due to construction delay. International

Journal of Integrated Engineering, 1.

AGC, A. 2005. The contractors guide to BIM. URL:

http://iweb. agc. org/iweb/Purchase/ProductDetail.

aspx.

ALI, H. B. M. 2015. Benefits of building Information

Modeling for Construction in Sudan. Sudan

University of Science and Technology.

ALINAITWE, H., APOLOT, R. & TINDIWENSI, D. 2013.

Investigation into the causes of delays and cost

overruns in Uganda's public sector construction

projects. Journal of Construction in Developing

Countries, 18, 33.

ARAYICI, Y., KHOSROWSHAHI, F., PONTING, A. M. &

MIHINDU, S. Towards implementation of building

information modelling in the construction industry.

Proceedings of The Fifth International Conference

on Construction in the 21st Century (CITC-V)

“Collaboration and Integration in Engineering,

Management and Technology”, May 20-22, 2009,

Istanbul, Turkey., 2009. 1342-1351.ASSAF, S. A.

& AL-HEJJI, S. 2006. Causes of delay in large

construction projects. International journal of

project management, 24, 349-357.

AUTODESK. 2014. The Value of BIM for Owners: Save

Time and Money During the Building Lifecycle

[Online]. Available:

http://damassets.autodesk.net/content/dam/autodesk

/www/solutions/bim/BIM_for_Owners.pdf.

[Accessed 23-Dec 2018].

AZHAR, S. 2011. Building information modeling (BIM):

Trends, benefits, risks, and challenges for the AEC

industry. Leadership and management in

engineering, 11, 241-252.

AZHAR, S., NADEEM, A., MOK, J. Y. & LEUNG, B. H.

Building Information Modeling (BIM): A new

paradigm for visual interactive modeling and

simulation for construction projects. Proc., First

International Conference on Construction in

Developing Countries (ICCIDC–I), Karachi,

Pakistan; 08/2008, 2008. 435-446.

BRYDE, D., BROQUETAS, M. & VOLM, J. M. 2013. The

project benefits of building information modelling

(BIM). International journal of project

management, 31, 971-980.

CANTARELLI, C. C. Cost overruns in Dutch transportation

infrastructure projects. Delft University of

Technology. Conference Presentation, 2009.

Citeseer, 19-20.

CIFE. 2007. CIFE Technical Reports [Online]. Available:

https://cife.stanford.edu/Publications/index.html

[Accessed 23-Dec 2018].

DOLOI, H. 2012. Cost overruns and failure in project

management: Understanding the roles of key

stakeholders in construction projects. Journal of

construction engineering and management, 139,

-279.

EASTMAN, C., TEICHOLZ, P., SACKS, R. & LISTON, K.

BIM handbook: A guide to building

information modeling for owners, managers,

Mahdi. M .et al. /ZJPAS: 2020, 32 (6): 185-196

ZANCO Journal of Pure and Applied Sciences 2020

designers, engineers and contractors, John Wiley &

Sons.

ENSHASSI, A., AL-NAJJAR, J. & KUMARASWAMY, M.

Delays and cost overruns in the construction

projects in the Gaza Strip. Journal of Financial

Management of Property and Construction, 14,

-151.

FLYVBJERG, B., SKAMRIS HOLM, M. K. & BUHL, S.

L. 2003. How common and how large are cost

overruns in transport infrastructure projects?

Transport reviews, 23, 71-88.

FRIMPONG, Y., OLUWOYE, J. & CRAWFORD, L. 2003.

Causes of delay and cost overruns in construction

of groundwater projects in a developing countries;

Ghana as a case study. International Journal of

project management, 21, 321-326.

GERGES, M., AUSTIN, S., MAYOUF, M., AHIAKWO,

O., JAEGER, M., SAAD, A. & GOHARY, T.-E.

An investigation into the implementation of

Building Information Modeling in the Middle East.

Journal of Information Technology in Construction

(ITcon), 22, 1-15.

GILLIGAN, B. & KUNZ, J. 2007. VDC use in 2007:

significant value, dramatic growth, and apparent

business opportunity. TR171, 36.

HAMADA, H., HARON, A., ZAKIRIA, Z. & HUMADA,

A. 2016. Benefits and Barriers of BIM Adoption in

the Iraqi Construction Firms. International Journal

of Innovative Research in Advanced Engineering,

, 76-84.

HARDIN, B. & MCCOOL, D. 2015. BIM and construction

management: proven tools, methods, and

workflows, John Wiley & Sons.

HASAN, A. N. & RASHEED, S. M. 2019. The Benefits of

and Challenges to Implement 5D BIM in

Construction Industry. Civil Engineering Journal,

, 412-421.

INNOVATION, C. C. 2007. Adopting BIM for facilities

management: Solutions for managing the Sydney

Opera House. Cooperative Research Center for

Construction Innovation, Brisbane, Australia.

JERNIGAN, F. 2007. BIG BIM little bim: The practical

approach to building information modeling, edn.

Site Press, Salisbury, Maryland, United Sates.

LE-HOAI, L., DAI LEE, Y. & LEE, J. Y. 2008. Delay and

cost overruns in Vietnam large construction

projects: A comparison with other selected

countries. KSCE journal of civil engineering, 12,

-377.

MAHDI, M. M. & ALI, N. S. 2019. Reducing Waste of

Construction Materials in Civil Engineering

Projects In Iraq. J ZANCO Journal of Pure Applied

Sciences, 31, 257-263.

OLAWALE, Y. A. & SUN, M. 2010. Cost and time control

of construction projects: inhibiting factors and

mitigating measures in practice. Construction

management and economics, 28, 509-526.

OSMAN, M. K. 2016. Implementation and potential

benefits of building information modeling (BIM) in

Sudan construction industry. Sudan University of

Science and Technology.

RAZAK BIN IBRAHIM, A., ROY, M. H., AHMED, Z. &

IMTIAZ, G. 2010. An investigation of the status of

the Malaysian construction industry.

Benchmarking: An International Journal, 17, 294-

SALEH, M. A. D. 2015. Barriers and Driving Factors for

Implementing Building Information Modelling

(BIM) in Libya. Eastern Mediterranean University

(EMU)-Doğu Akdeniz Üniversitesi (DAÜ).

SAMBASIVAN, M. & SOON, Y. W. 2007. Causes and

effects of delays in Malaysian construction

industry. International Journal of project

management, 25, 517-526.

WALI, K. I. & OTHMAN, S. A. 2019. Schedule Risk

Analysis Using Monte Carlo Simulation for

Residential Projects. J ZANCO Journal of Pure

Applied Sciences, 31, 90-103.

YAN, H. & DEMIAN, P. 2008. Benefits and barriers of

building information modelling.

YOCKEY, R. D., (2017). SPSS Demystified: A Simple

Guide and Reference, 2nd ed. 2017, United

Kingdom: Taylor & Francis, (2017).

https://books.google.iq/books?id=m6Q5DwAAQB

AJ

Published

2020-12-20

How to Cite

Mahmood Maad Mahdi, Khalil Ismail Wali, & Burog Abdullhalim Yuosif. (2020). Minimizing Time and Cost in The Iraqi AEC industry by Adopting Building Information Modeling (BIM) Technique. Zanco Journal of Pure and Applied Sciences, 32(6), 185–196. https://doi.org/10.21271/ZJPAS.32.6.19