Minimizing Time and Cost in The Iraqi AEC industry by Adopting Building Information Modeling (BIM) Technique.
DOI:
https://doi.org/10.21271/ZJPAS.32.6.19Keywords:
Building Information Modeling, Construction Management, Cost overrun, Sustainability, Time overrun.Abstract
The Architectural, Engineering, and Construction (AEC) industry is essential for its direct influence on the development of any
country, particularly in terms of economy. Thus, problems related to cost and time arise as a global phenomenon in this industry,
particularly in the third world countries like Iraq. The Building information modeling (BIM) technique is considered as the most
adequate technique that overcomes the problems facing the AEC industry. This paper aimed to assess the causes of cost issues and
time delays in the Iraqi AEC industry and to outline the BIM concept and the benefits of its application for solving these
problems. This paper consists of two parts; the first one is the quantitative approach, which was adopted for data collection
through a specially designed questionnaire form; these questionnaires were spread among 50 of the top and middle management in
different construction companies, and other experts in the arena of AEC industry. The results of the statistical analysis showed
that the highest influential factors on cost and time overrun are: inadequate planning and scheduling, selecting inefficient
contractors, change orders, and the errors and mistakes in preparing the bill of quantities and materials (BOQ/BOM) with relative
importance index (RII) of 0.98, 0.87, 0.83 and 0.82 respectively. The second part of this paper reviewed the benefits of applying
BIM and highly recommend this technology to improve the local AEC industry. The application of the BIM technique will lead to
more sustainable design, construction, and project delivery in the Iraqi projects. This paper presents a significant set of
recommendations that demonstrate how BIM technique can be applied to overcome the challenges of the AEC industry in Iraq. It
unlocks the door for further authentic researches on the adoption of BIM technique as an influential and exceptional tool to point
out the issues related to time and cost in the AEC industry in Iraq.
References
ABDUL RAHMAN, I., MEMON, A. H., KARIM, A. &
TARMIZI, A. 2013. Significant factors causing
cost overruns in large construction projects in
Malaysia. Journal of Applied Science, 13, 286-293.
ABDULLAH, M., AZIS, A. A. & RAHMAN, I. A. 2009.
Potential effects on large mara construction
projects due to construction delay. International
Journal of Integrated Engineering, 1.
AGC, A. 2005. The contractors guide to BIM. URL:
http://iweb. agc. org/iweb/Purchase/ProductDetail.
aspx.
ALI, H. B. M. 2015. Benefits of building Information
Modeling for Construction in Sudan. Sudan
University of Science and Technology.
ALINAITWE, H., APOLOT, R. & TINDIWENSI, D. 2013.
Investigation into the causes of delays and cost
overruns in Uganda's public sector construction
projects. Journal of Construction in Developing
Countries, 18, 33.
ARAYICI, Y., KHOSROWSHAHI, F., PONTING, A. M. &
MIHINDU, S. Towards implementation of building
information modelling in the construction industry.
Proceedings of The Fifth International Conference
on Construction in the 21st Century (CITC-V)
“Collaboration and Integration in Engineering,
Management and Technology”, May 20-22, 2009,
Istanbul, Turkey., 2009. 1342-1351.ASSAF, S. A.
& AL-HEJJI, S. 2006. Causes of delay in large
construction projects. International journal of
project management, 24, 349-357.
AUTODESK. 2014. The Value of BIM for Owners: Save
Time and Money During the Building Lifecycle
[Online]. Available:
http://damassets.autodesk.net/content/dam/autodesk
/www/solutions/bim/BIM_for_Owners.pdf.
[Accessed 23-Dec 2018].
AZHAR, S. 2011. Building information modeling (BIM):
Trends, benefits, risks, and challenges for the AEC
industry. Leadership and management in
engineering, 11, 241-252.
AZHAR, S., NADEEM, A., MOK, J. Y. & LEUNG, B. H.
Building Information Modeling (BIM): A new
paradigm for visual interactive modeling and
simulation for construction projects. Proc., First
International Conference on Construction in
Developing Countries (ICCIDC–I), Karachi,
Pakistan; 08/2008, 2008. 435-446.
BRYDE, D., BROQUETAS, M. & VOLM, J. M. 2013. The
project benefits of building information modelling
(BIM). International journal of project
management, 31, 971-980.
CANTARELLI, C. C. Cost overruns in Dutch transportation
infrastructure projects. Delft University of
Technology. Conference Presentation, 2009.
Citeseer, 19-20.
CIFE. 2007. CIFE Technical Reports [Online]. Available:
https://cife.stanford.edu/Publications/index.html
[Accessed 23-Dec 2018].
DOLOI, H. 2012. Cost overruns and failure in project
management: Understanding the roles of key
stakeholders in construction projects. Journal of
construction engineering and management, 139,
-279.
EASTMAN, C., TEICHOLZ, P., SACKS, R. & LISTON, K.
BIM handbook: A guide to building
information modeling for owners, managers,
Mahdi. M .et al. /ZJPAS: 2020, 32 (6): 185-196
ZANCO Journal of Pure and Applied Sciences 2020
designers, engineers and contractors, John Wiley &
Sons.
ENSHASSI, A., AL-NAJJAR, J. & KUMARASWAMY, M.
Delays and cost overruns in the construction
projects in the Gaza Strip. Journal of Financial
Management of Property and Construction, 14,
-151.
FLYVBJERG, B., SKAMRIS HOLM, M. K. & BUHL, S.
L. 2003. How common and how large are cost
overruns in transport infrastructure projects?
Transport reviews, 23, 71-88.
FRIMPONG, Y., OLUWOYE, J. & CRAWFORD, L. 2003.
Causes of delay and cost overruns in construction
of groundwater projects in a developing countries;
Ghana as a case study. International Journal of
project management, 21, 321-326.
GERGES, M., AUSTIN, S., MAYOUF, M., AHIAKWO,
O., JAEGER, M., SAAD, A. & GOHARY, T.-E.
An investigation into the implementation of
Building Information Modeling in the Middle East.
Journal of Information Technology in Construction
(ITcon), 22, 1-15.
GILLIGAN, B. & KUNZ, J. 2007. VDC use in 2007:
significant value, dramatic growth, and apparent
business opportunity. TR171, 36.
HAMADA, H., HARON, A., ZAKIRIA, Z. & HUMADA,
A. 2016. Benefits and Barriers of BIM Adoption in
the Iraqi Construction Firms. International Journal
of Innovative Research in Advanced Engineering,
, 76-84.
HARDIN, B. & MCCOOL, D. 2015. BIM and construction
management: proven tools, methods, and
workflows, John Wiley & Sons.
HASAN, A. N. & RASHEED, S. M. 2019. The Benefits of
and Challenges to Implement 5D BIM in
Construction Industry. Civil Engineering Journal,
, 412-421.
INNOVATION, C. C. 2007. Adopting BIM for facilities
management: Solutions for managing the Sydney
Opera House. Cooperative Research Center for
Construction Innovation, Brisbane, Australia.
JERNIGAN, F. 2007. BIG BIM little bim: The practical
approach to building information modeling, edn.
Site Press, Salisbury, Maryland, United Sates.
LE-HOAI, L., DAI LEE, Y. & LEE, J. Y. 2008. Delay and
cost overruns in Vietnam large construction
projects: A comparison with other selected
countries. KSCE journal of civil engineering, 12,
-377.
MAHDI, M. M. & ALI, N. S. 2019. Reducing Waste of
Construction Materials in Civil Engineering
Projects In Iraq. J ZANCO Journal of Pure Applied
Sciences, 31, 257-263.
OLAWALE, Y. A. & SUN, M. 2010. Cost and time control
of construction projects: inhibiting factors and
mitigating measures in practice. Construction
management and economics, 28, 509-526.
OSMAN, M. K. 2016. Implementation and potential
benefits of building information modeling (BIM) in
Sudan construction industry. Sudan University of
Science and Technology.
RAZAK BIN IBRAHIM, A., ROY, M. H., AHMED, Z. &
IMTIAZ, G. 2010. An investigation of the status of
the Malaysian construction industry.
Benchmarking: An International Journal, 17, 294-
SALEH, M. A. D. 2015. Barriers and Driving Factors for
Implementing Building Information Modelling
(BIM) in Libya. Eastern Mediterranean University
(EMU)-Doğu Akdeniz Üniversitesi (DAÜ).
SAMBASIVAN, M. & SOON, Y. W. 2007. Causes and
effects of delays in Malaysian construction
industry. International Journal of project
management, 25, 517-526.
WALI, K. I. & OTHMAN, S. A. 2019. Schedule Risk
Analysis Using Monte Carlo Simulation for
Residential Projects. J ZANCO Journal of Pure
Applied Sciences, 31, 90-103.
YAN, H. & DEMIAN, P. 2008. Benefits and barriers of
building information modelling.
YOCKEY, R. D., (2017). SPSS Demystified: A Simple
Guide and Reference, 2nd ed. 2017, United
Kingdom: Taylor & Francis, (2017).
https://books.google.iq/books?id=m6Q5DwAAQB
AJ
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2020 Mahmood Maad Mahdi, Khalil Ismail Wali, Burog Abdullhalim Yuosif

This work is licensed under a Creative Commons Attribution 4.0 International License.